Traceable topology
Eight strings of 17 modules, four strings per inverter, and one string connected to each MPPT circuit.
Technical drawing sample
A controlled A3 drawing for the representative 74.8 kWp rooftop example. It shows the string-to-MPPT allocation, conversion equipment, AC collection, point of connection, monitoring path, and design hold points.
Representative concept - not a completed project. Not for construction, procurement, or energisation.
Drawing sheet
The complete representative power and monitoring architecture is presented together with its controlled design notes and project-specific hold points.
Drawing controls
Eight strings of 17 modules, four strings per inverter, and one string connected to each MPPT circuit.
Two strings would produce 26.24 A at maximum-power current, above the representative inverter's published 26 A MPPT limit.
Cables, protective devices, fault duty, earthing, RCD, SPD, export control, fire access, and grid settings require verified project inputs.
Project drawing support
Available inputs should include the site layout, equipment data sheets, point of connection, existing SLD, cable routes, fault level, and applicable local requirements.